You are here

Daily Road Report, August 22, 2019

For immediate release: August 21, 2019 - 3:00pm
TC19-634

*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.
 
NEW
 
CLARENCE AVE S NB & SB PARKING LANES CLOSED FROM 3RD ST E TO 8TH ST E
(Building move)
Start: August 22, 3:00 a.m. End: August 22, 7:00 a.m.
 
MCORMOND DR NB LANES CLOSED FROM WILLOWGROVE BLVD TO ADDISON RD
(Microsurfacing)
2-way traffic maintained in SB lanes
Start: August 22, 7:00 a.m. End: August 23, 7:00 a.m.
 
NELSON RD SB LEFT TURN LANE CLOSED AT ATTRIDGE DR
(Signal base concrete work)
Start: August 22, 9:00 a.m. End: August 22, 3:00 p.m.
 
TAYLOR ST E EB LANES CLOSED FROM CAIRNS AVE TO EWART AVE
(Manhole repairs)
Start: August 22, 9:00 a.m. End: August 22, 5:00 p.m.
 
PRESTON AVE S NB & SB MEDIAN LANES CLOSED FROM WILSON CRES TO ARLINGTON AVE
(Sanitary lining)
Start: August 22, 9:00 a.m. End: August 22, 5:00 p.m.
 
CENTRAL AVE NB & SB MEDIAN LANES CLOSED FROM 112TH ST W TO GRAY AVE
(Line flushing)
Start: August 22, 9:00 a.m. End: August 22, 6:00 p.m.
 
3RD AVE N ROAD CLOSED FROM PRINCESS ST TO DUCHESS ST
(Water main replacement)
Start: August 22, 9:00 a.m. End: August 23, 4:00 p.m.
 
CLARENCE AVE S NB & SB MEDIAN LANES CLOSED FROM CIRCLE DR S TO BRAND RD
(Street light replacement)
Start: August 22, 10:00 a.m. End: August 22, 12:00 p.m.
 
ONGOING
 
MCORMOND DR SB LANES CLOSED FROM NELSON RD TO ATTRIDGE DR
(Microsurfacing)
Start: August 21, 7:00 a.m. End: August 22, 7:00 a.m.
 
MARQUIS DR W WB MEDIAN & NEXT LANE CLOSED & EB MEDIAN LANE CLOSED FROM IDYLWYLD DR N TO THATCHER AVE
(Water & sewer work)
Start: August 19, 9:00 a.m. End: August 22, 5:00 p.m.
 
TAYLOR ST E WB CLOSED FROM JACKSON AVE TO CUMBERLAND AVE S
(Resurfacing)
2-way traffic maintained in EB lanes
Start: August 20, 9:00 a.m. End: August 23, 7:00 a.m.
 
LENORE DR EB & WB MEDIAN & NEXT LANES CLOSED FROM WARMAN RD TO PRIMROSE DR
(Roadway resurfacing)
Start: August 21, 7:00 a.m. End: August 23, 4:00 p.m.
 
HIGHWAY 5 WB ROAD CLOSED FROM RANGE ROAD 3043 TO HIGHWAY 41
(Resurfacing)
Two-way traffic maintained in WB lanes.
Temporary traffic lights in place allowing 1-way traffic only
Start: August 21, 7:00 a.m. End: August 23, 6:00 p.m.
 
3RD AVE N SB LANES CLOSED FROM 24TH ST E TO 23RD ST E
(Resurfacing)
2-way traffic maintained in NB lanes
Start: August 21, 11:00 a.m. End: August 24, 7:00 a.m.
 
33RD ST W EB PARKING & CURB LANE CLOSED FROM CONFEDERATION DR TO JUNOR AVE
(Concrete repairs)
Start: August 20, 7:00 a.m. End: August 30, 5:00 p.m.
 
7TH AVE N ROAD CLOSED FROM QUEEN ST TO WARBURTON ST
(Water main replacement)
Start: July 2, 7:00 a.m. End: September 2, 5:00 p.m.
 
WANUSKEWIN RD NB LANES CLOSED AT 71ST ST E 
(Road construction)  
2-way traffic maintained in SB lanes 
Start: August 6, 9:00 a.m. End: October 6, 4:00 p.m.
 
SID BUCKWOLD BRIDGE NB & SB LANES RESTRICTED 
(Bridge upgrades) 
Lanes restricted in both directions; NB lanes zipper merge near 8th St. SB single lane starting at 20th St. 
Start: April 14, 8:30 a.m. End: October 31, 5:00 p.m.

MCORMOND DR INTERSECTION CLOSED AT BRIGHTON CMN 
(Construction)
Start: July 25, 7:00 a.m. End: October 31, 5:00 p.m.
 
COLLEGE DR WB SPEED REDUCTION FROM MCORMOND DR TO MCKERCHER DR
(Construction)
Start: July 5, 9:00 a.m. End: November 30, 5:00 p.m.
 
AVE H S INTERSECTION CLOSED AT 11TH ST W
(Construction)
Start: March 11, 7:00 a.m. End: August 31, 5:00 p.m.
 
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.
Slow down, pay attention and respect work zones. Watch for pedestrians and work crews, and for everyone’s safety, please obey all detours, signs and barriers.