NEW

22ND ST E WB LANES CLOSED FROM 3RD AVE N TO 2ND AVE N
(Crane lift)
Start: September 20, 4:30 a.m. End: September 20, 7:00 a.m.

Hwy 16 NB MEDIAN & LEFT TURN LANE CLOSED AT BEAM RD
(Milling & paving roadway)
Start: September 20, 7:00 a.m. End: September 20, 3:30 p.m.
 
SPADINA CRES E ROAD CLOSED FROM 2ND AVE S TO 3RD AVE S
(Sign installation)
Start: September 20, 7:00 a.m. End: September 20, 4:00 p.m.

CENTRAL AVE SB LANES CLOSED FROM POWE ST TO 115TH ST W
(Sewer connection replacement)
Start: September 20, 8:00 a.m. End: September 20, 5:00 p.m.
 
8TH ST E WB PARKING LANE CLOSED FROM LANSDOWNE AVE TO DUFFERIN AVE
(Concrete work)
Start: September 20, 9:00 a.m. End: September 27, 9:00 p.m.
 
PRESTON AVE S NB CURB LANE CLOSED AT 7TH ST E
(Core sampling)
Start: September 20, 1:30 p.m. End: September 20, 3:30 p.m.
 
ONGOING
 
IDYLWYLD DR N SB CURB LANE CLOSED AT 23RD ST
(Planter removal)
Start: September 19, 9:00 a.m. End: September 20, 6:00 p.m.

LORNE AVE INTERSECTION CLOSED AT 2ND ST W
(Water main replacement)
Start: September 16, 7:00 a.m. End: September 21, 5:00 p.m.

IDYLWYLD DR N NB CURB LANE CLOSED FROM 25TH ST E TO 31ST ST E
(Concrete replacement)
Start: September 16, 9:00 a.m. End: September 25, 5:00 p.m.

CLARENCE AVE S SB LEFT TURN LANE CLOSED AT BRAND RD
(Roadway construction)
Start: August 26, 7:00 a.m. End: September 26, 4:00 p.m.

CONFEDERATION DR SB PARKING LANE CLOSED FROM CONFEDERATION PL TO BORDEN PL
(Sidewalk replacement)
Start: September 19, 7:00 a.m. End: September 26, 5:00 p.m.

7TH AVE N ROAD CLOSED FROM PRINCESS ST TO QUEEN ST
(Water main replacement)
Start: September 6, 7:00 a.m. End: September 30, 5:00 p.m.

WANUSKEWIN RD NB LANES CLOSED AT 71ST ST E; TWO WAY TRAFFIC SET IN SB LANES
(Road construction)
Start: August 6, 9:00 a.m. End: October 6, 4:00 p.m.

SID BUCKWOLD BRIDGE NB & SB LANES RESTRICTED
(Bridge upgrades)
Lanes restricted in both directions; NB lanes zipper merge near 8th St. SB single lane starting at 20th St.
Start: April 14, 8:30 a.m. End: October 31, 5:00 p.m.

MCORMOND DR INTERSECTION CLOSED AT BRIGHTON CMN
(Construction)
Start: July 25, 7:00 a.m. End: October 31, 5:00 p.m.

COLLEGE DR WB SPEED REDUCTION FROM MCORMOND DR TO MCKERCHER DR
(Construction)
Start: July 5, 9:00 a.m. End: November 30, 5:00 p.m.

All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.